How do I allow for several design reviews without inventing a fixed approval duration?
Plan the number of review rounds and the time you will take for each, and ask the designer for their turnaround. Do not invent a duration for any third-party approval; record it as an unknown with a dependency instead.
Quick Answer
Plan the number of review rounds and the time you will take for each, and ask the designer for their turnaround. Do not invent a duration for any third-party approval; record it as an unknown with a dependency instead.
Plan your own review time honestly
Decide how long you will take to review each issue, including consulting anyone else who has a view, and put that on the programme.
Owner review time is frequently shown as a few days and takes several weeks. Planning realistically is better than planning optimistically and slipping.
Ask the designer for theirs
Ask how long they need to incorporate comments and reissue, and how many rounds are included in their appointment.
Ask what happens if more rounds are needed, both in fee and in time.
Do not guess third-party durations
Where an approval by an authority, a landlord or a building management is involved, record it as an activity with an unknown duration rather than assigning a figure.
Ask the relevant party what their process involves and what they can tell you about typical timescales, and record their answer as their statement rather than as your assumption.
Ask who will collect and consolidate comments at each review, and confirm that person has the authority to send them. Review rounds extend most often because comments arrive late and separately rather than because the review itself took long.
Manage the dependency
Identify what can proceed while an approval is outstanding and what cannot, so a delay affects as little as possible.
Ask what would be at risk if an approval took considerably longer than hoped, and whether anything could be ordered or started at your own risk.
Review the programme when each approval is submitted and again when it is determined, rather than leaving the original assumption in place. This keeps the programme honest; the requirements and timescales of any approval remain matters for the appointed consultants and the relevant authorities.
Need help with your property?
Discuss your project with MANZIL
Tell us where the villa is, what exists today and what you’re planning.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.





