How do I coordinate furniture procurement with the workstation power plan?

Fix the furniture selection before the power layout is finalised, because the power positions depend on the desk dimensions, the leg arrangement and the way cables are managed within the furniture. Ordering in the wrong order produces sockets in unusable positions.

Quick Answer

Fix the furniture selection before the power layout is finalised, because the power positions depend on the desk dimensions, the leg arrangement and the way cables are managed within the furniture. Ordering in the wrong order produces sockets in unusable positions.

Establish the dependency

Ask the designer what they need from the furniture supplier: desk dimensions, leg and frame positions, cable tray locations, and the point at which power enters each desk.

Ask the furniture supplier what they assume about the power supply: floor boxes, a connection from a wall, or a fixed position beneath each desk. Both parties usually assume the other will adapt.

Fix the layout before the power design

Agree the desk layout with real dimensions on a plan, including the clusters and how they are joined. Power positions follow from that layout and cannot be sensibly designed without it.

Ask what happens if the layout changes after the floor boxes are installed. In a raised floor this may be straightforward; in a solid floor it usually is not, and the answer should inform how firmly the layout is fixed.

Coordinate the details in one drawing

Ask for a single drawing showing the furniture, the power and data positions, and the route into each desk. Two separate drawings produced by two suppliers is how the coordination fails.

Ask who is responsible for the final connection into the furniture and whether that is included in either scope. This gap between the electrical contractor and the furniture supplier is the most common one.

Confirm before either is ordered

Ask both parties to confirm the coordinated drawing in writing before manufacture or installation begins.

Check the sample desk against the actual power position before the full order. This prevents a visible and permanent problem; the electrical design, capacity and compliance remain matters for the qualified engineer and installer.

Need help with your property?

Discuss your project with MANZIL

Tell us where the office is, what exists today and what you’re planning.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact