How do I record resident access constraints for a building-wide survey?

Record each unit's access position as a fact rather than a judgement: access granted and when, access refused, no response, or conditions attached. Record what constraint applies and who to contact, and keep the reasons out of it.

Quick Answer

Record each unit's access position as a fact rather than a judgement: access granted and when, access refused, no response, or conditions attached. Record what constraint applies and who to contact, and keep the reasons out of it.

Record the position for each unit

Record each unit with its access status, the dates attempted, how contact was made and the outcome.

Use consistent categories so the coverage can be reported without describing individual residents' circumstances.

Record the conditions rather than the reasons

Where a resident sets a condition, record the condition: a particular day, a time, presence required, or a request about photography.

Do not record the reason a resident gives, since that is usually personal and is not needed to arrange access.

Record what could not be inspected

Record which parts of each unit were not accessed and why, in factual terms, so the survey's coverage is clear.

Record what remains to be inspected and whether a further attempt is planned.

Agree who holds the access record and how long it is kept, since it contains information about residents' arrangements. Restricting it to those who need it for the survey is both appropriate and easier to justify if questioned.

Ask how long the survey period runs and whether residents who could not be reached will be offered another opportunity. A single attempt recorded as no access understates what a reasonable effort would have achieved.

Report coverage rather than individuals

Report the survey in terms of coverage achieved and areas outstanding, rather than naming units that refused.

Where a pattern of no response occurs, consider whether the contact method is reaching people rather than assuming refusal.

Agree in advance how many attempts constitute a reasonable effort and what happens afterwards, since that decision belongs to management rather than to the surveyor attending on the day. This keeps the record fair and usable; rights of access, notice requirements and any lease obligation remain matters for the management and its advisers.

Need help with your property?

Discuss your project with MANZIL

Tell us where your residential building is, what records you have and how it is currently being used.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact