How do I record the price assumptions for restricted working hours?

Ask the contractor to state which hours they priced, what they assumed about access and noise restrictions, and what would change if the actual restrictions differ. Get the assumption written into the quotation rather than discussed and forgotten.

Quick Answer

Ask the contractor to state which hours they priced, what they assumed about access and noise restrictions, and what would change if the actual restrictions differ. Get the assumption written into the quotation rather than discussed and forgotten.

Ask what hours were assumed

Ask which working hours and days the price is based on, and whether it assumes continuous access or restricted periods. Contractors frequently price on normal working patterns without checking the building's rules.

Confirm the actual restrictions with the building management or the relevant authority yourself, and give that answer to every contractor pricing the work so they are all on the same basis.

Ask what the restriction costs

Ask how the price would change if noisy work can only happen in limited windows, or if access is unavailable on certain days. Ask for the effect on both cost and duration.

Ask which specific activities are affected. Usually only a small part of the programme is genuinely restricted, and knowing which part prevents the whole project being repriced on a general assumption.

Record the assumption in the document

Ask for the assumed hours to be written into the quotation as a stated condition. An assumption that exists only in a conversation becomes a claim later.

Ask what evidence would be needed if the restriction turns out to be different, and agree how a change would be valued before work starts.

Log the hours actually worked each week against the assumed pattern. Where restrictions turn out to be tighter than assumed, a contemporaneous record of what was permitted and when is far more persuasive than a reconstruction attempted at the end of the project.

Keep the confirmations together

Keep the building's written statement of permitted hours, the contractor's stated assumption and any variation agreed, in one file.

Log any day when work is stopped or restricted, with the reason. This keeps the commercial position evidenced; permitted working hours and any enforcement are matters for the building management and the relevant authorities.

Need help with your property?

Discuss your project with MANZIL

Tell us where the apartment is, what exists today and what you’re planning.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact