What should I agree about moving furniture between rooms during phased work?
Agree what moves, when, who moves it, where it goes and who is responsible for damage. Record the condition of each significant item before it is moved, and keep valuables and fragile items out of the process entirely.
Quick Answer
Agree what moves, when, who moves it, where it goes and who is responsible for damage. Record the condition of each significant item before it is moved, and keep valuables and fragile items out of the process entirely.
Agree what moves and what does not
List the items to be moved between phases, and separately list what you will remove yourself: valuables, documents, electronics, anything fragile or irreplaceable.
Agree that nothing on your list is touched by the contractor. This is simpler and safer than agreeing special care.
Agree who moves it and when
Agree whether the contractor moves furniture as part of their scope or whether you arrange it, and confirm it in writing. Assumptions on this point are common and expensive.
Agree the dates for each movement, tied to the phase changes, and what notice you receive. Furniture moved too early occupies a room that is about to be worked on.
Agree how it is protected
Agree how items are wrapped, where they are placed and how they are protected from dust and from the work in the adjacent room.
Ask whether anything needs to be dismantled and who reassembles it, and whether any item is too heavy or too large to move safely at all.
Ask where furniture will be stored if no room is available, and what that would cost. External storage for part of a phased project is sometimes cheaper and considerably safer than repeatedly moving items between rooms that are about to be worked on.
Record the condition first
Photograph each significant item before it is moved, including existing marks, with the date.
Agree how damage is reported and by when, and who bears the cost. Where the contractor moves items, ask whether their insurance covers them.
Keep the list, the photographs and the agreement in one file. This keeps a phased project workable; liability for any damage and the adequacy of any insurance remain matters for the contractor and your own advisers.
Need help with your property?
Discuss your project with MANZIL
Tell us where your apartment is, what records you have and how it is currently being used.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.





