How do I identify decisions that need the building owner's input early?
Identify early anything that changes the structure, the exterior, shared services, or the use of the property, and anything the building owner has a stated interest in. Ask them in writing before design proceeds, because a late refusal can undo months of work.
Quick Answer
Identify early anything that changes the structure, the exterior, shared services, or the use of the property, and anything the building owner has a stated interest in. Ask them in writing before design proceeds, because a late refusal can undo months of work.
Identify what is not yours to decide
Ask your designer which elements typically require the building owner's or landlord's agreement: structural alterations, changes to the facade, work affecting shared services, drainage, ventilation, and anything visible from outside.
Ask also about work that is unlikely to need agreement, so you do not delay the whole project seeking permission for items that do not require it.
Ask early and in writing
Send a clear description with a drawing, rather than a general enquiry. A specific request receives a specific answer; a vague one usually receives silence or a cautious refusal.
Ask what information they require and how long their process takes. That timescale belongs on your programme as an activity with a dependency, not as an assumption that an answer will arrive when needed.
Ask what the answer depends on
Ask whether approval is conditional on anything: a particular contractor, insurance, a deposit, restricted working hours or reinstatement obligations. These conditions frequently affect cost and should be known before pricing.
Ask whether their agreement covers the work as described only, and what would require a further approval. Design development often changes something the original approval assumed.
Ask whether the building owner charges for reviewing a request and how long their answer remains valid. Approvals sometimes lapse if work does not start within a period, which matters if your programme slips, and it is far easier to establish that condition at the outset than to discover it after a delay.
Keep the record
Keep the request, the drawing sent, the response and any conditions in one file, and give the conditions to your contractor.
Do not start work that depends on an outstanding approval. This protects the project; the interpretation of any lease, building rule or regulatory requirement remains a matter for the building owner, the relevant authorities and your own advisers.
Need help with your property?
Discuss your project with MANZIL
Tell us where the villa is, what exists today and what you’re planning.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.