How do I prepare a room-by-room specification I can give to several contractors?
Write one specification per room with the same headings, each stating the required outcome, materials or standards where chosen, exclusions and what is provisional. Give the identical document to every contractor so quotations can be compared line by line.
Quick Answer
Write one specification per room with the same headings, each stating the required outcome, materials or standards where chosen, exclusions and what is provisional. Give the identical document to every contractor so quotations can be compared line by line.
Use a fixed structure
For each room list: existing conditions and photographs, work to be done by element (floor, walls, ceiling, doors, windows, joinery, sanitaryware, lighting, sockets, ventilation), finishes with selections or allowances, items retained, items removed and who disposes of them.
State the outcome, not only the item
Describe what each element must achieve, such as a level surface, matching colour, access for maintenance, or a replaced item using an existing position. Where a product is selected, give the reference and supplier; where it is not, state an allowance and what it covers.
Identify what is not included
Mark exclusions, such as items supplied by you, work by others and any assumptions about concealed conditions. Mark provisional items so contractors price them consistently.
Add project-level information
Include access, working hours, building rules, protection requirements, deliveries, waste, programme constraints and how variations are instructed.
Add drawings and photographs
Attach plans marked with room names, dimensions you have verified and photographs of existing conditions. Label everything consistently.
Ask contractors to return their questions in writing and to list any assumptions they made beyond the specification. Reviewing those assumptions before choosing shows where a low quotation depends on something you did not intend.
Ask each contractor to mark any item in the specification they consider unclear or unbuildable as written. Their comments before pricing are much cheaper to resolve than changes discovered after the contract has been agreed.
Issue and answer questions together
Send the same package, set a question deadline and share every question and answer with all contractors.
The specification helps comparison and reduces assumptions; technical design, compliance and the suitability of methods remain the responsibility of the designer and qualified contractors who review and complete it.
Need help with your property?
Discuss your project with MANZIL
Tell us where the villa is, what exists today and what you’re planning.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.