What should I agree between the barista-equipment supplier and fit-out team?

Agree in writing what the equipment needs and who provides it: water treatment, drainage, power, clearances, ventilation and the exact counter cut-outs. Most coffee installations fail at the boundary between the equipment supplier's scope and the fit-out contractor's.

Quick Answer

Agree in writing what the equipment needs and who provides it: water treatment, drainage, power, clearances, ventilation and the exact counter cut-outs. Most coffee installations fail at the boundary between the equipment supplier's scope and the fit-out contractor's.

Get the equipment requirements in writing early

Ask the equipment supplier for the technical requirements of each item: dimensions, weight, power, water supply, drainage, water quality and any clearance or ventilation requirement.

Ask for these before the counter is designed. Coffee equipment has specific requirements that are difficult to accommodate once joinery is manufactured and services are installed.

Define the boundary of each scope

Agree item by item who supplies and who installs: water treatment, isolators, drainage connections, counter cut-outs, support beneath heavy equipment and the final connections.

Ask each party to confirm in writing what they are not doing. The gap between two scopes, rather than an overlap, is what leaves an installation incomplete on the day before opening.

Coordinate the counter itself

Give the joiner the equipment dimensions and cut-out requirements, and ask for a drawing showing each machine in position with its services.

Ask about the weight of the equipment and whether the counter requires additional support, and about access beneath for servicing and for the water treatment system.

Ask who is responsible if the equipment is damaged during installation or if a service connection turns out to be inadequate. Where the equipment supplier and the fit-out contractor each blame the other, an agreement recorded in advance is the only thing that resolves it quickly.

Plan the installation sequence

Agree who attends on the installation day and in what order, and what must be complete before the equipment supplier arrives.

Agree who commissions the equipment, who trains staff and what records you receive. Confirm the whole arrangement in writing before the counter is manufactured. This prevents the common failure at handover; the technical requirements, water quality, drainage and any hygiene or safety obligation remain matters for the qualified specialists.

Need help with your property?

Discuss your project with MANZIL

Tell us where the restaurant / café is, what exists today and what you’re planning.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact