What should I ask when a connection appointment depends on unfinished civil work?

Ask exactly what civil work must be complete, who inspects it, and what happens if the appointment is attended and the work is not ready. Then put that inspection on the programme as its own activity with a date.

Quick Answer

Ask exactly what civil work must be complete, who inspects it, and what happens if the appointment is attended and the work is not ready. Then put that inspection on the programme as its own activity with a date.

Ask what must be complete

Ask the provider for a written list of what they require: excavation, ducting, chambers, backfill, reinstatement, a connection point in a specific position, or a prepared meter position.

Ask for the tolerance on any dimension or position, since a duct that ends a short distance from where they expect it can cause a refusal.

Ask who checks and when

Ask whether an inspection takes place before the connection appointment, who carries it out, and how much notice they need.

Ask what evidence they accept, such as photographs of the open trench, and arrange for those to be taken before backfilling.

Ask what a failed appointment costs

Ask what happens if they attend and the work is not ready: whether a charge applies, how quickly a new date is available and whether the original position in the queue is lost.

This answer determines how much contingency to leave between completing the civil work and the appointment.

Ask whether the provider will accept photographic evidence of completed work in place of a site inspection, and in what form. Where they will, arranging the photographs correctly before backfilling can remove a scheduling dependency entirely.

Programme it properly

Put the civil work, the inspection and the connection on the programme as separate activities with the dependencies shown, rather than as a single item.

Agree who confirms readiness and to whom, and ask for confirmation a few days before the appointment rather than on the day.

Keep the provider's requirements, your photographs and the correspondence in one file. This keeps the connection on track; the provider's technical requirements and any regulatory approval remain matters for that provider and the relevant authorities.

Need help with your property?

Discuss your project with MANZIL

Tell us where the villa is, what exists today and what you’re planning.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact