What should I compare between the final account and the approved change log?

Check every item in the final account against an instruction you approved, at the value that was agreed. Work through the change log in order, mark each item as matched, different or unknown, and raise the differences as one clear list.

Quick Answer

Check every item in the final account against an instruction you approved, at the value that was agreed. Work through the change log in order, mark each item as matched, different or unknown, and raise the differences as one clear list.

Prepare both documents first

Ask for the final account itemised so that each change can be identified separately, with reference to the instruction that created it. A single lump sum for variations cannot be checked.

Put your change log in the same order and make sure it records the date, the instruction, who approved it and the agreed value or the basis for valuing it.

Match item by item

Work down the list marking each account item as agreed and matching, agreed but priced differently, or not recognised. Do not attempt to resolve anything until the whole comparison is done.

Look for items priced twice: a change included in a revised scope and then charged again separately. This is the most common error and the easiest to demonstrate.

Check the items that never had a price

Identify approved instructions that were never valued, and instructions valued but never approved. Both are normal in practice, and both need resolving before the account is settled.

Check omissions as well as additions. Work removed from the scope should reduce the account, and it is often missing from the adjustment.

Check the dates. An item priced before an instruction existed, or a change valued after the work was already complete, usually indicates a record-keeping problem rather than dishonesty, and it is easier to resolve once identified.

Raise differences in one clear list

Send a single schedule showing each disputed item, the account figure, your figure and the document you rely on. Separate arithmetic differences from disagreements about scope or entitlement.

Confirm the undisputed total so that agreed amounts are not delayed by contested items. This gives you a defensible comparison; the valuation of the work and any contractual entitlement are matters for your commercial and legal advisers.

Need help with your property?

Discuss your project with MANZIL

Tell us where your commercial building / space is, what records you have and how it is currently being used.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact