What should I include in daily room-release records during phased hotel work?

Record which rooms are released to the contractor, which are returned to the hotel, and the condition and readiness of each at the moment of transfer. A daily record prevents disputes about when a room changed hands and in what state.

Quick Answer

Record which rooms are released to the contractor, which are returned to the hotel, and the condition and readiness of each at the moment of transfer. A daily record prevents disputes about when a room changed hands and in what state.

Record the transfers each day

Record each room released to the contractor with the date, time and who authorised it, and each room returned with the same detail.

Record the room's status: fully complete, complete except for named items, or released for further work.

Record the condition at each transfer

Photograph the room at each transfer, so the condition when it left the hotel and when it came back is documented.

Note any damage, any outstanding item and anything left in the room.

Record readiness for use

For returned rooms, record what has been checked: cleaning, systems working, keys, safe, telephone, television, air conditioning and hot water.

Record who carried out the check and whether the room is released for sale or held pending an item.

Ask housekeeping to sign the return of each room as well as the project team, since a room accepted by the project as complete is not necessarily ready to sell. Two signatures on the transfer make that distinction explicit rather than assumed.

Keep it as one daily document

Keep a single daily record covering all transfers rather than separate notes, so the position for any date can be established quickly.

Circulate it to operations, housekeeping and the project team the same day.

Note which rooms are adjacent to active work each day, since that information is what reservations need in order to allocate guests sensibly, and it changes as the work moves. This keeps the two operations aligned; the technical completion of any room and any safety requirement remain matters for the qualified professionals.

Need help with your property?

Discuss your project with MANZIL

Tell us where your commercial building / space is, what records you have and how it is currently being used.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact