What should I record when the responsible contractor changes after handover?
Record who was responsible before, who is responsible now, from what date, and for which items. Ask both parties to confirm the position in writing, and keep the original handover documents unchanged.
Quick Answer
Record who was responsible before, who is responsible now, from what date, and for which items. Ask both parties to confirm the position in writing, and keep the original handover documents unchanged.
Record the changeover precisely
Note the date responsibility changed, what prompted it, and which elements the new party has taken on. Where only part of the work transfers, list what does and what does not.
Ask for written confirmation from both the outgoing and incoming parties. A change confirmed by only one side leaves a gap that usually appears at the moment a defect is reported.
Record the condition at the changeover
Walk the property and record the state of the relevant work with photographs and a written list of open items, dated.
Ask the incoming party to confirm the list. This protects everyone, because it establishes what was outstanding at the point of transfer rather than reconstructing it later.
Keep the original documents intact
Do not alter the original handover pack, certificates or warranties. Add the change as a new record referencing them.
Note which warranties remain with the original party and which, if any, transfer. Product warranties, installation obligations and service agreements may each be treated differently.
Ask who holds the remaining defect obligations for work completed before the change, and whether the incoming party has accepted them. This is the single question that most often goes unasked, and it surfaces only when a defect from the earlier period is reported.
Establish who to contact for what
Ask for a single contact list showing who now handles each system or element, and keep it with the handover file.
Ask what happens to items already reported but not yet resolved. This keeps responsibility traceable; the legal effect of any transfer of obligations and the enforceability of any warranty remain matters for your own advisers.
Need help with your property?
Discuss your project with MANZIL
Tell us where your villa is, what records you have and how it is currently being used.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.