DDA building modification: design review, permit and completion
5 steps · 9 documents, 1 drawing, 1 calculation, 2 things to have in place
DDA Building Modification (design review, permit, completion) · Dubai Development Authority (DDA) · Dubai Civil Defence (DCD)
Sources checked:
How this approval works
The official pages list these steps but don't say what order to follow.
Steps without a confirmed order
- Create a new Building Modification project on the DDA Zoning e-Services portal for the design review
- Select the Permit application under that project and upload the required documents
- Select the Completion Certificate application under the project and upload the required documents
- Raise the structural inspection request through the DDA Zoning Portal
- The consultant approves the inspection online, confirming it is consistent with the approved drawings and specifications
What is this approval?DDA Building Modification (design review, permit, completion)
- This guide explains, in plain terms, what official sources say about this approval: what to prepare and how the application works.
- It involves: DDA permit and/or approval for the works.
- It involves: DDA Building Modification permit (Building Department).
- It involves: DDA structural inspection (standard, late or holiday).
When might I need it?7 points to check
- Official sources state that this approval is required for the works it covers.
- They describe it for work such as: additional floor, mezzanine, new construction, room extension, structural opening, warehouse subdivision.
- Works without the appropriate permit or approval will be stopped.
- Applies to structural modification or changes, change in usage, mezzanine addition, and addition, omission, merging or separation of units or areas, even for small units and units in shopping malls.
- Design review and permit are available after the building completion certificate has been issued.
- All DDA comments or conditions must be cleared before the completion request is submitted.
- The request is accepted only if the site plan is valid.
- Whether it applies to your project depends on your property, its location and the work you plan. MANZIL Approvals can check this for your project.
Who can apply?Not confirmed yet
- We couldn't confirm from official sources who submits the application.
- Authorities involved: Dubai Development Authority (DDA) (building control); Dubai Civil Defence (DCD) (fire and life safety).
What should I prepare?9 documents, 1 drawing, 1 calculation, 2 things to have in place
Documents
- Building Modification application
- Consultant appointment letter from the owner or tenant
- Dubai Civil Defence NOC (if it applies to your case)
- Appointment letter signed by the owner, consultant and contractor
- Site mobilization layout (if it applies to your case)
- Building Modification completion request
- Civil Defence completion certificate (if it applies to your case)
- NOC from the building owner to issue the completion certificate
- Compliance certificate from the main consultant
Drawings
- Approved stamped drawings and proposed drawings highlighting the changes (architectural, structural, mechanical)
Calculations
- Structural calculations and models (if it applies to your case)
Before you apply
- Design review and permit are for completed buildings, after the building completion certificate.
- All DDA comments or conditions must be cleared before the completion request is submitted.
What happens afterwards?1 step after approval
- Inspection: DDA structural inspection (standard, late or holiday).
What is still to confirm?4 things we couldn't confirm
- This guide explains what official sources confirm. It doesn't cover everything about this approval.
- We couldn't confirm what happens at completion for this approval.
- We couldn't confirm whether you need a consultant for this approval.
- The official pages list these steps but don't say what order to follow.
- Official sources disagree on this point. Please confirm with the authority.
- Official sources disagree on one point of this route, so that detail is not shown. Please confirm it with the authority.
Official sources
- Building Modification - Design
- DDA Circular 621: Structural Inspection Approval Process Update (30 May 2025)
- DDA Circular 338: Amendments in Fit out Permit Process (11 December 2019)
- Building Modification - Completion
- Building Modification - Permit
- TECOM Group
- DDA Circular 428: Construction without permits / approvals (26 January 2023)
- DDA form ZA-DC-F-69 Issue 10: Building Modification Design Approval Request
MANZIL is an independent guide. Follow the authority’s current instructions for your property and proposed work. Explore your approval journey → · Discuss this guide with the MANZIL team →