Dubai Municipality building completion certificate
10 steps · 3 documents
Dubai Municipality building completion certificate · Dubai Municipality (DM) · Dubai Civil Defence (DCD) · RTA
Sources checked:
How this approval works
Follow these steps in this order.
Select the type of completion transaction
Log in and select the type of completion transaction.
Upload the documents
Upload the documents (contractor applications only).
Pay the inspection request
Pay the inspection request.
Receive the Dubai Municipality reply
The reply is either accepted with a site inspection date or returned with no visit.
Meet the unified inspection committee at the site
Meet the unified inspection committee at the site.
Pay and download the completion certificate
If approved with no comments that prevent issue, pay and download the completion certificate.
Steps without a confirmed order
- Log in, fill the required fields and attach an authorization letter if applying on the owner's behalf
- Receive the payment request by SMS
- Meet the unified inspection committee at the site
- If approved, download the completion certificate
What is this approval?Dubai Municipality building completion certificate
- This guide explains, in plain terms, what official sources say about this approval: what to prepare and how the application works.
- It involves: DM building completion certificate.
- It involves: Unified inspection committee site inspection.
- It involves: SIRA no-objection certificate for buildings specified in Circulars 170/2009 and 204/2016.
- It involves: Unified inspection committee: DM Building Activities Control and Survey, Dubai Civil Defence, RTA, Etisalat and du.
- It involves: Building completion certificate.
- It involves: Civil defence completion certificate.
- It involves: Final survey certificate.
When might I need it?7 points to check
- Official sources state that this approval is required for the works it covers.
- They describe it for work such as: additional floor, façade modification, interior fit-out, mezzanine, partition, room extension, staircase, structural opening, villa extension, wall removal.
- The system notifies the contractor of an owner application and allows a legal response period before the completion procedures begin.
- The building may be operated and used only once the SIRA approval is obtained.
- The contracting engineer must accompany the committee on the site visit; the consulting engineer need not be present.
- A contractor or consultant refusal that relates to financial or contractual matters does not stop the completion certificate being issued to the owner.
- There is no partial completion certificate for modification, addition and decorative works.
- Whether it applies to your project depends on your property, its location and the work you plan. MANZIL Approvals can check this for your project.
Who can apply?Official sources require a contractor for this approval.
- Official sources require a contractor for this approval.
- Official sources mention an engineering consultant as optional.
- Authorities involved: Dubai Municipality (DM) (building control); Dubai Civil Defence (DCD) (fire and life safety); RTA (road access).
What should I prepare?3 documents
Documents
- Consultant Approval Form (permits issued with a consultant) - contractor applicant (if it applies to your case)
- Dubai Civil Defence documents per its inspection checklist, where applicable - contractor applicant (if it applies to your case)
- Authorization letter from the project owner - applicant acting for the owner (if it applies to your case)
What happens afterwards?6 steps after approval
- Inspection: Unified inspection committee site inspection.
- Inspection: Unified inspection committee: DM Building Activities Control and Survey, Dubai Civil Defence, RTA, Etisalat and du.
- Completion: DM building completion certificate.
- Completion: Building completion certificate.
- Completion: Civil defence completion certificate.
- Completion: Final survey certificate.
What is still to confirm?4 things we couldn't confirm
- This guide explains what official sources confirm. It doesn't cover everything about this approval.
- We couldn't confirm which drawings this approval needs.
- We couldn't confirm whether any calculations are needed for this approval.
- We couldn't confirm what must be in place first from official sources.
- Civil Defence involvement depends on the project. We could not confirm whether Dubai Civil Defence approval is a separate filing for projects permitted through Dubai Municipality. Please confirm with your consultant or DM/DCD.
- Official sources disagree on this point. Please confirm with the authority.
- Official sources disagree on one point of this route, so that detail is not shown. Please confirm it with the authority.