DDA fit-out permit and completion
1 step · 11 documents, 9 drawings, 1 thing to have in place
DDA fit-out permit and completion · Dubai Development Authority (DDA) · Dubai Civil Defence (DCD) · Dubai Municipality (DM) · Dubai Health Authority (DHA)
Sources checked:
How this approval works
The official pages list these steps but don't say what order to follow.
Steps without a confirmed order
- Log in to Zoning e-Services, select the Completion Certificate application under the Fit-out project and upload the required documents
What is this approval?DDA fit-out permit and completion
- This guide explains, in plain terms, what official sources say about this approval: what to prepare and how the application works.
- It involves: DDA fit-out permit.
- It involves: No-objection from the main contractor, main consultant and plot owner (if the building has no completion certificate yet).
- It involves: Dubai Civil Defence completion certificate (before the fit-out completion certificate).
- It involves: DDA fit-out completion certificate.
- It involves: NOC from the building owner.
- It involves: NOCs from relevant authorities, as per the NOC matrix (if applicable).
- It involves: Dubai Municipality Food Control Section NOC.
- It involves: Dubai Municipality Environmental Department NOC.
- It involves: Dubai Health Authority NOC.
- It involves: Dubai Municipality Public Health and Safety Department NOC.
- It involves: DDA fit-out completion inspection.
When might I need it?8 points to check
- Official sources state that this approval is required for the works it covers.
- Official sources describe it for these property types: clinic, factory, gym, office, restaurant / café, salon, warehouse.
- They describe it for work such as: additional floor, interior fit-out, mezzanine, office fit-out, restaurant fit-out, room extension, structural opening.
- Adding structural elements, changing the use or additional GFA needs a Building Modification request.
- The fit-out scope must contain no structural change (for example a mezzanine floor or staircase), no change of use and no change in GFA or parking.
- The building must already have its completion certificate.
- The matrix lists none of the Food Control, Public Health and Safety, Environmental or Dubai Health Authority NOCs for offices; other requirements still apply.
- DDA-approved drawings must be available at site during the inspection.
- Whether it applies to your project depends on your property, its location and the work you plan. MANZIL Approvals can check this for your project.
Who can apply?Not confirmed yet
- We couldn't confirm from official sources who submits the application.
- Authorities involved: Dubai Development Authority (DDA) (building control); Dubai Civil Defence (DCD) (fire and life safety); Dubai Municipality (DM) (other NOCs, environmental); Dubai Health Authority (DHA) (other NOCs).
What should I prepare?11 documents, 9 drawings, 1 thing to have in place
Documents
- Fit-out permit request
- Contractor appointment letter by the tenant
- No-objection from the main contractor, main consultant and plot owner (if the building has no completion certificate yet) (if it applies to your case)
- Fit-out completion certificate application
- NOC from the tenant to issue the completion
- Dubai Civil Defence completion certificate
- Contractor appointment by the tenant
- Copy of EJARI
- NOC from the building owner
- NOCs from relevant authorities as per the NOC matrix (if it applies to your case)
- Tenant licence for the unit
Drawings
- Approved stamped drawings and proposed drawings (Circular 400)
- Cover sheet and schedule of drawings
- Approved stamped drawings
- Proposed key plan and architectural layout
- Partition layouts (approved and proposed)
- Proposed furniture, flooring and ceiling layouts
- Proposed sections AA and BB
- HVAC drawings (food and beverages only) (if it applies to your case)
- Drainage floor plans, approved and proposed (retail) (if it applies to your case)
Before you apply
- The Dubai Civil Defence completion certificate is required before the fit-out completion certificate is obtained.
What happens afterwards?3 steps after approval
- Inspection: DDA fit-out completion inspection.
- Completion: Dubai Civil Defence completion certificate (before the fit-out completion certificate).
- Completion: DDA fit-out completion certificate.
What is still to confirm?3 things we couldn't confirm
- This guide explains what official sources confirm. It doesn't cover everything about this approval.
- We couldn't confirm whether any calculations are needed for this approval.
- We couldn't confirm whether you need a consultant for this approval.
- The official pages list these steps but don't say what order to follow.
Official sources
- DDA form ZA-DC-F-38 Issue 14: Fit-out Permit Request
- DDA service page: Fit-Out Permit
- DDA template ZA-DC-T-123 Issue 3: Fit-out Permit submission required drawings
- DDA Fit-out NOC Matrix (Appendix 1)
- DDA service page: Fit-Out Completion Certificate
- DDA form ZA-DC-F-39 Issue 11: Fit-out Completion Certificate Request
- TECOM Group
MANZIL is an independent guide. Follow the authority’s current instructions for your property and proposed work. Explore your approval journey → · Discuss this guide with the MANZIL team →