How do I keep a record of rejected materials before they leave the site?
Photograph and list the rejected material before it leaves, recording the product, quantity, batch or delivery reference and the reason for rejection. Keep the record with the correspondence, because the material itself will not be available later.
Quick Answer
Photograph and list the rejected material before it leaves, recording the product, quantity, batch or delivery reference and the reason for rejection. Keep the record with the correspondence, because the material itself will not be available later.
Record it while it is still there
Photograph the material in position, including labels, batch markings and packaging. Once it is collected, the only remaining evidence is what you captured.
Record the quantity and where it came from, referencing the delivery note or order. Without this, a later credit or replacement discussion becomes difficult.
State the reason clearly
Write the reason in observable terms: damaged on arrival, wrong reference, colour outside the approved range, quantity short, or condition unsuitable. Avoid vague wording such as not acceptable.
Where the rejection is about appearance, photograph the material next to the approved sample in the same light. This single image resolves most disagreements.
Confirm who decided and who agreed
Note who rejected it, who from the supplier or contractor was informed, and what they said. Ask for their acknowledgement in writing before collection.
Ask whether any of the material is being retained for reference, and where. Keeping one rejected piece is often worth more than any description.
Ask whether the rejected material came from the same batch as anything already installed. Where it did, the installed work deserves a check before it is accepted, because a batch problem rarely affects only the pieces that happened to be opened last.
Track the replacement
Record the agreed replacement, its expected date and any effect on the programme, and keep this with the rejection record.
Check the replacement against the same approved sample on arrival. This keeps the supply chain accountable; the technical acceptability of any material and any commercial credit remain matters for the responsible professionals and your advisers.
Need help with your property?
Discuss your project with MANZIL
Tell us where your villa is, what records you have and how it is currently being used.
WhatsApp MANZILMANZIL Approvals
Not sure which approvals apply to your property?
Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.
Explore MANZIL ApprovalsExplore by property
More answers for the place you’re working on.