How do I plan room refurbishment around confirmed guest bookings?

Work from the confirmed booking position rather than from occupancy forecasts, and take rooms out of service in blocks that reflect how the contractor can work. Agree a cut-off after which rooms are released to the contractor and cannot be sold.

Quick Answer

Work from the confirmed booking position rather than from occupancy forecasts, and take rooms out of service in blocks that reflect how the contractor can work. Agree a cut-off after which rooms are released to the contractor and cannot be sold.

Start from confirmed bookings

Take the booking position by room type and by date, and identify the periods where confirmed occupancy is lowest.

Distinguish confirmed bookings from forecast occupancy, since a plan built on forecast can collapse when bookings arrive.

Agree how rooms are released

Agree how many rooms the contractor needs at once and for how long, since working room by room is far slower and more expensive than working in blocks.

Agree a cut-off date after which each block is removed from sale, and make sure reservations cannot sell a room in a released block.

Consider the rooms around the work

Consider the rooms adjacent to and below the work area, since noise and access usually make those unsellable or at least unsuitable for some guests.

Agree how those rooms are managed: withheld, sold with disclosure, or allocated to less sensitive guests.

Ask what happens if occupancy rises unexpectedly and rooms are needed back, since that pressure always arrives at some point. Agreeing in advance whether a released block can be recovered, and at what cost, prevents the decision being made under pressure.

Plan the guest experience

Agree the contractor's access routes so they do not pass guest areas, and agree working hours that suit an occupied hotel.

Agree how guests are informed and what is offered if they are affected.

Review the plan weekly against the actual booking position, and agree who has authority to adjust the release schedule, since this decision sits between operations and the project and frequently has no owner. This keeps the refurbishment and the hotel working together; fire, escape and safety arrangements during the works remain matters for the qualified professionals and the relevant authorities.

Need help with your property?

Discuss your project with MANZIL

Tell us where the commercial building / space is, what exists today and what you’re planning.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact