How do I record discrepancies between delivered metalwork and approved samples?

Record the difference factually with photographs of the delivered item beside the approved sample, stating what differs and by how much. Report it before installation, because metalwork is far harder to correct once fixed.

Quick Answer

Record the difference factually with photographs of the delivered item beside the approved sample, stating what differs and by how much. Report it before installation, because metalwork is far harder to correct once fixed.

Compare against the approved sample

Retrieve the approved sample and the approval record, including the finish reference, gloss level and any dimensional information agreed.

Place the delivered item and the sample together in the same light and photograph them in one frame. A single comparative image resolves most disagreements faster than any description.

Describe what differs

State the difference in observable terms: colour, texture, gloss, weld appearance, edge treatment, dimension or fixing arrangement. Avoid characterising it as acceptable or unacceptable.

Where the difference is dimensional, measure it and state where. Where it is visual, photograph it at the viewing distance as well as close up.

Report before anything is fixed

Notify the supplier and the contractor in writing the same day, with the photographs and the approval reference, and ask for the item not to be installed pending a response.

Ask whether other items from the same batch are affected, and ask for them to be checked before delivery rather than after.

Ask whether the difference arises from the fabrication or from the finishing process, since the two are often carried out by different companies. Establishing where it originated usually determines how quickly it can be corrected and who arranges the correction.

Record the outcome

Record what is agreed: acceptance, rework, replacement or a revised approval, with the reason and the date.

Where an item is accepted despite a difference, record that it was accepted knowingly so it is not raised again as a defect at handover.

Keep the sample, the photographs and the correspondence together. This keeps quality controllable; the technical acceptability of any variation and the adequacy of the fabrication remain matters for the responsible professionals.

Need help with your property?

Discuss your project with MANZIL

Tell us where your villa is, what records you have and how it is currently being used.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact