What should I ask before work is accelerated with additional shifts?

Ask what the additional shifts will actually achieve, what they cost, who supervises them, and what effect they have on quality, noise and the building's rules. Acceleration that produces rework saves nothing.

Quick Answer

Ask what the additional shifts will actually achieve, what they cost, who supervises them, and what effect they have on quality, noise and the building's rules. Acceleration that produces rework saves nothing.

Ask what the time saving is

Ask which activities will be worked additionally and how much time that recovers on the completion date, not on individual tasks. Extra hours on work that is not governing the date change nothing.

Ask what limits the saving: drying and curing periods, inspections, deliveries or decisions still outstanding. Many programmes cannot be compressed by labour alone.

Ask about supervision and quality

Ask who supervises the additional shifts and whether the same supervision is present. Unsupervised evening or weekend working is where quality problems most often originate.

Ask how work carried out on those shifts is inspected, and whether anything would be covered up without the usual checks.

Ask what the building permits

Confirm with the building management or the relevant authority what hours are permitted, before agreeing anything. Do not rely on the contractor's assumption.

Ask what notice neighbours or other occupants require, and who gives it. An acceleration that generates complaints can be stopped entirely, which costs more time than it saved.

Ask whether any additional labour will be people already familiar with the project or a new team brought in for the period. Unfamiliar workers on a partly completed site need supervision and induction, and the time spent providing it reduces the saving the additional shift was meant to deliver.

Ask what it costs and who pays

Ask for the cost in writing and on what basis it is charged, and establish who bears it. That depends on why the delay occurred, and it should be agreed before the shifts start rather than argued afterwards.

Record what was agreed, what was worked and what was achieved. This keeps acceleration accountable; entitlement to time or cost, and the technical adequacy of accelerated work, remain matters for your advisers and the qualified professionals involved.

Need help with your property?

Discuss your project with MANZIL

Tell us where your villa is, what records you have and how it is currently being used.

WhatsApp MANZIL

MANZIL Approvals

Not sure which approvals apply to your property?

Explore general guidance for your property, planned work and location. Project-specific approvals still need verification.

Explore MANZIL Approvals

Explore by property

More answers for the place you’re working on.

View all property types
Contact