Programme & Procurement questions
9 published questions
Villa
Agree a written schedule of what each delivery contains and check each one against it on arrival. Record the missing items as a running list with expected dates, and keep that…
Villa
Keep them as two separate written steps. Approving a sample confirms what the material should look like; authorising an order commits money and quantity. Combining them means a…
Villa
Ask for the proposal in writing with the specific measures, what each one depends on, and what it costs. Record it alongside the original programme rather than replacing it, so…
Villa
Photograph the packaging, the labels and the damage before anything is moved or discarded, and record the date opened against the date delivered. Report it immediately in writing…
Villa
It should tell you what is happening in the next few weeks, what it depends on, what affects your use of the property, and what decisions or deliveries are needed from you.…
Villa
Ask what the additional shifts will actually achieve, what they cost, who supervises them, and what effect they have on quality, noise and the building's rules. Acceleration that…
Villa
Ask why it changed, how the new reference differs from the approved sample, and to see a physical sample from the new batch before anything is delivered. Do not accept a change…
Villa
Ask who decides the sequence, what each trade needs from the others, and what the consequence is of working simultaneously in a confined space. Congestion in a small room usually…
Villa
Ask what the resequencing changes, what it saves, and what risks it introduces. Ask specifically whether any work would be done out of its normal order and what that means for…